Franna, Emmi (2019) Analisis faktor-faktor penyebab change order dan pengaruhnya terhadap waktu penyelesaian proyek pembangunan gedung sekolah x di provinsi Bangka Belitung. Masters thesis, Universitas Pelita Harapan.
![Title [thumbnail of Title]](http://repository.uph.edu/style/images/fileicons/text.png)
Pernyataan.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (1MB)
Preview
Abstrak.pdf
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (183kB) | Preview
Preview
Kata Pengantar.pdf
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (966kB) | Preview
Preview
BAB 1.pdf
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (198kB) | Preview
![Chapter 2 [thumbnail of Chapter 2]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 2.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (443kB)
![Chapter 3 [thumbnail of Chapter 3]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 3.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (368kB)
![Chapter 4 [thumbnail of Chapter 4]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 4.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (557kB)
![Chapter 5 [thumbnail of Chapter 5]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 5.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (182kB)
Preview
DAFTAR PUSTAKA.pdf
Available under License Creative Commons Attribution Non-commercial No Derivatives.
Download (241kB) | Preview
Abstract
Change order often occurs at the time when project is in progress. This
change occurs when the signing of the work contract had been made. The X
school building in Bangka Belitung Islands Province was built with a structural
plan for 8-storey, but for the first phase 4-storey had been built, with school land
area of 2,968 m2 and each floor area 1.242,8m2. In the implementation of the
construction of school X experienced a change order which is design changes,
acceleration of work schedules, addition of scope of work, incompatibility of
pictures with field conditions and others that take effects on project completion
time of X school building which leads to delay the completion time cause by
change order factors.
The purpose of this study is to analyze the factors that cause change orders
and their effects on project completion time of X school buildings in Bangka
Belitung Islands Province. This study examines from a variety of literary sources
namely reference books and highlights relevant research results in the past 10
years related to the causes of change orders and their effects on project
completion time of school building.
The research methodology used is a quantitative research method that
examines the collected literature studies. The analysis results of the factors
causing change order and its effect on project completion time in this study, there
are 4 variable that take effect on project completion time of X school building in
Bangka Belitung Island Province that was increased the scope of work by 58.9%,
the performance of the owner or representative of the owner by 17.7%, investment
funds which is not enough by 10% and cashflow that does not match the actual
progress of 2.9% .
And with these results is expected to become a benchmark for the next
project so that it goes well. / Change order sering terjadi pada saat pelaksanaan proyek berlangsung.
Perubahan ini terjadi pada saat penandatangan kontrak kerja sudah dilakukan.
Gedung sekolah X di Provinsi Kepulauan Bangka Belitung dibangun dengan
perencanaan struktur 8 lantai, tetapi yang tahap pertama dibangun 4 lantai terlebih
dahulu. Dengan luas lahan sekolah 2.968 m2, dan luas tiap-tiap lantainya 1.242,8
m2. Dalam pelaksanaan pembangunan sekolah X mengalami change order yaitu
perubahan desain, percepatan jadwal pekerjaan, penambahan scope pekerjaan,
ketidaksesuaian gambar dengan kondisi lapangan, dan lain sebagainya yang
berpengaruh terhadap waktu penyelesaian proyek pembangunan gedung sekolah
X yang dapat mengalami keterlambatan penyelesaian proyek dengan adanya
faktor-faktor penyebab change order.
Tujuan penelitian ini menganalisis faktor penyebab change order dan
pengaruhnya terhadap waktu penyelesaian proyek pembangunan gedung sekolah
X di Provinsi Kepulauan Bangka Belitung. Penelitian ini mengkaji berbagai
sumber literatur yaitu buku referensi dan mengangkat hasil penelitian yang
relevan dalam 10 tahun terakhir terkait penyebab change order dan pengaruhnya
terhadap waktu penyelesaian proyek pembangunan gedung sekolah.
Metodologi penelitian yang digunakan adalah metode penelitian kuantitatif
yang mengkaji kuesioner yang dikumpulkan. Hasil analisis faktor-faktor
penyebab change order dan pengaruhnya terhadap waktu penyelesaian pada
penelitian ini yaitu didapatkan 4 variabel yang berpengaruh terhadap waktu
penyelesaian dalam proyek pembangunan gedung sekolah X di Provinsi
Kepulauan Bangka Belitung yaitu penambahan scope pekerjaan sebesar 58,9%,
kinerja pemilik atau wakil pemilik sebesar 17,7%, dana investasi yang tidak
cukup sebesar 10% dan cashflow yang tidak sesuai progress aktual sebesar 2,9%.
Serta diharapkan hasil analisis ini menjadi tolak ukur pada proyek
selanjutnya agar berjalan dengan baik.
Item Type: | Thesis (Masters) |
---|---|
Creators: | Creators NIM Email ORCID Franna, Emmi NIM01629170028 UNSPECIFIED UNSPECIFIED |
Contributors: | Contribution Contributors NIDN/NIDK Email Thesis advisor Idawati, Lusiana NIDN0329096601 UNSPECIFIED |
Uncontrolled Keywords: | change order ; time schedule ; project ; building ; school |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | University Subject > Historic > Faculty/School > Master of Civil Engineering Historic > Faculty/School > Master of Civil Engineering |
Depositing User: | Users 3196 not found. |
Date Deposited: | 10 Jan 2020 08:14 |
Last Modified: | 09 Nov 2021 06:37 |
URI: | http://repository.uph.edu/id/eprint/6051 |