Hadiyat, Firsya (2016) Analisis pengendalian material pipa dalam proyek engineering procurement construction (EPC) minyak dan gas di proyek SMK 3 Balikpapan di PT Meindo Elang Indah. Masters thesis, Universitas Pelita Harapan.
![Title [thumbnail of Title]](http://repository.uph.edu/style/images/fileicons/text.png)
title.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (2MB)
![Abstract [thumbnail of Abstract]](http://repository.uph.edu/style/images/fileicons/text.png)
abstract.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (301kB)
![ToC [thumbnail of ToC]](http://repository.uph.edu/style/images/fileicons/text.png)
toc.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (380kB)
![Chapter 1 [thumbnail of Chapter 1]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 1 Pendahuluan.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (1MB)
![Chapter 2 [thumbnail of Chapter 2]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 2 Landasan Teori.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (790kB)
![Chapter 3 [thumbnail of Chapter 3]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 3 Metodologi Penelitian.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (747kB)
![Chapter 4 [thumbnail of Chapter 4]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 4.Analisas dan pembahasan.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (611kB)
![Chapter 5 [thumbnail of Chapter 5]](http://repository.uph.edu/style/images/fileicons/text.png)
BAB 5.Kesimpulan.pdf
Restricted to Registered users only
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (368kB)
Preview
Daftar Pustaka.pdf
Available under License Creative Commons Attribution Non-commercial Share Alike.
Download (362kB) | Preview
Abstract
Currently the development of the projects of oil and gas is undergoing
rapid development, however if not supported by good management then the
course of development project will not be maximized. EPC project is a project in
where the contractor running the project with scope of responsibility for
completion of work includes design studies, procurement of materials and
construction as well as planning of these three activities. Pattern of EPC project
that the owners give credence to the EPC contractor from initial design
engineering, procurement of materials and equipment, and carry out the
construction work. Hence the performance of the work can be lead to the
achievement of certain target with technical specifications required by the owner.
EPC project is a project with high complexity due to dealing with high
risk jobs, demands high quality, schedule is relatively short, associated with huge
costs and a series of activities that commonly performed only once time. So that
the construction management plays an important role for successes of this EPC
project, how the resources involved in the project can be applied as appropriate.
The topic of thesis is related to controlling of material pipe in EPC project
oil and gas in PT. Meindo Elang Indah, specific data collected from one of
projects called South Mahakam Phase 3 (SMK3). At end obtained 3 main
variables that affected to overall performance of project and impacted to losses
on project. The results of this tesis are expected to be useful and become inputsiv
for company in where the research was conducted and could also be a reference
for other Contractor when executing a project. / Dewasa ini pembangunan pada proyek-proyek minyak dan gas sedang
mengalami perkembangan yang pesat, namun bila tidak di dukung dengan
manajemen yang baik maka jalannya pembangunan proyek tersebut tidak akan
maksimal. Proyek EPC adalah suatu proyek dimana kontraktor mengerjakan
proyek dengan ruang lingkup tanggung jawab penyelesaian pekerjaan meliputi
studi rekayasa, pengadaan material dan konstruksi serta perencanaan dari ketiga
aktivitas tersebut. Pada pola proyek EPC, pemilik memberi kepercayaan kepada
kontraktor untuk mengerjakan proyek mulai dari tahap rekayasa, melakukan
pengadaan material dan peralatan, dan melaksanakan pekerjaan konstruksi.
Sehingga kinerja pekerjaan yang telah dikerjakan tersebut dapat menghasilkan
pencapaian target tertentu dengan spesifikasi teknis yang dikehendaki oleh
pemilik proyek.
Proyek EPC merupakan proyek dengan kompleksitas yang tinggi karena
berhubungan dengan resiko pekerjaan yang tinggi, tuntutan kualitas yang tinggi,
waktu pengerjaan yang relatif pendek, berhubungan dengan biaya yang besar dan
merupakan suatu rangkaian kegiatan yang umumnya hanya satu kali
dilaksanakan. Sehingga manajemen konstruksi memegang peranan penting dalam
mensukseskan proyek EPC ini, bagaimana sumber daya yang terlibat dalam
proyek dapat diaplikasikan secara tepat.
Tesis ini mengangkat topik pengendalian material pipa di proyek EPC
minyak dan gas di PT. Meindo Elang Indah, spesifik data diambil dari salah satu
proyek yaitu South Mahakam Phase 3 (SMK3) dan dari penelitian didapat 3ii
variabel utama yang mempengaruhi kinerja keseluruhan proyek yang berakibat
pada kerugian pada proyek tersebut, yang selanjutnya didetailkan dalam tesis ini.
Hasil penelitian ini diharapkan dapat bermanfaat dan menjadi masukan bagi
perusahaan tempat penelitian ini dilakukan dan juga bisa menjadi referensi bagi
perusahaan kontraktor lainnya ketika mengeksekusi suatu proyek khususnya
proyek minyak dan gas
Item Type: | Thesis (Masters) |
---|---|
Creators: | Creators NIM Email ORCID Hadiyat, Firsya NIM00000001820 UNSPECIFIED UNSPECIFIED |
Contributors: | Contribution Contributors NIDN/NIDK Email Thesis advisor Simanjuntak, Manlian Ronald A. NIDN0330117401 UNSPECIFIED |
Additional Information: | T 29-12 HAD a |
Uncontrolled Keywords: | Controlling of pipe material ; which could be impacted to losses and schedule completion of project |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | University Subject > Historic > Faculty/School > Master of Civil Engineering Historic > Faculty/School > Master of Civil Engineering |